20 December 2008

Quick update

Well as we head into the festive hurry, a quick update of progress on site. A skeleton staff is currently working and it seems they will work right through Christmas. We can expect girders to be lifted in the run up to Christmas. As it stands, we still have 10 girders in place, with the 11th almost ready to be lifted. Cladding of the first few girders is underway, and the first 9 girders have now been connected by the fore-girders forming the compression ring that will ultimately hold the flood lights. All that's left for me to do is to wish everyone a merry Christmas. I'll be back before new year with a full update.