The big news on site is that the new replay screens are being installed. Floodlights and other electronic equipment are also being put in place. Otherwise a similar scene from last weekend with a bit more cladding having been done and almost all PTFE membranes having been installed. There are now only 3 girders on which cladding has not yet started. 10 girders in all still need cladding completion. Around the stadium, roads are being dug up to be relayed and earthworks are being done for the landscaping of the precinct. The new pedestrian bridge is now almost complete, with paving progressing smoothly.
27 April 2009
Viewing screens going in.